RIVERFRONT REDEVELOPMENT PROJECT UPDATES
FREE SMOKE & CARBON MONOXIDE DETECTOR INSTALLATION
TO REPORT A BOROUGH STREET LIGHT OUTAGE:
RESOLUTION ADOPTING AFFORDABLE HOUSING OBLIGATION FOR SEA BRIGHT, 1-21-25 (pdf)
RIVERFRONT REDEVELOPMENT PROJECT UPDATES

As a courtesy to our residents find, below, updates regarding the progress of the Haven at Sea Bright Project, the current riverfront redevelopment project being developed by Denholtz Properties and Toll Brothers, located on the west side of the Borough's Downtown Area. Please continue to visit this page for the most up to date information. If you have additional questions please contact Borough Administrator, Rachel Giolitto at rgiolitto@seabrightnj.org or 732-842-0099 ext. 113.
 
March 14, 2025
  • Sanitary & stormwater installation and grading is in progress.
  • Curb installation is ready to begin at the north end of site, pending warmer weather.
  • The bulkhead is nearly complete.
  • Boardwalk pile and support installation is in progress.
  • Electric, gas, water, and cable designs have been finalized, with gas work ready to begin following curb installation.
  • Foundation pile installation should begin in April/May.
  • Kayak launch surface is in progress.
 
February 21, 2025
  • Sanitary & stormwater installation and grading are in progress.
  • Curb installation is ready to begin at the north end of the site, pending warmer weather.
  • The bulkhead is roughly 2/3 complete. Denholtz is continuing boardwalk pile installation and king piles. The contractor is running into some minor obstructions which is slowing the progress.
  • Building foundation pile designs are in progress. Denholtz anticipates additional pile installation in March/April. We will schedule a pre-con meeting prior to this installation.
  • Meetings will be held on site throughout February to finalize designs for electric, gas, and water services.
 
February 7, 2025
  • Sanitary & stormwater installation and grading in progress.
  • Curb installation ready to begin at north end of site, pending warmer weather.
  • Bulkhead at roughly 2/3 completion, contractor will begin the boardwalk piles on Monday 2/10, weather permitting.
  • Test piles were completed on 1/28 and the results will be used by structural engineer to finalize the pile designs for the building foundations. We anticipate additional pile installation in March/April.
  • Meetings to be held on site throughout February to finalize designs for electric, gas, and water services.
January 24, 2025
  • Sanitary & stormwater installation, grading of building pads, as well as bulkhead sheeting installation remain ongoing.
  • Bulkhead cap installation as well as bulkhead tie rods and walers are now in progress.
  • Bulkhead king pile installation in progress.
  • Test pile installation has been rescheduled for the week of 1/27 due to extreme cold.

January 10, 2025

  • Sanitary & stormwater installation, grading of building pads, as well as bulkhead sheeting installation remain ongoing.
  • Bulkhead cap installation as well as bulkhead tie rods and walers are now in progress.
  • Test piles remain scheduled for January 13, 2025.
  • Inspection letters were sent out to property owners from Dayton Services, the company contracted by Denholtz Properties to perform vibration monitoring services. If you did not receive a letter and believe you should have of or if you have any questions regarding the inspection, please contact Alyssa with Dayton Services at 856-824-1010.
January 3, 2025
  • Denholtz Properties is continuing sanitary & stormwater installation, grading of building pads, as well as bulkhead sheeting installation.
  • Bulkhead cap installation as well as bulkhead tie rods and walers will begin.
  • Test piles are scheduled for January 13, 2025.
  • Inspection letters were sent out to property owners from Dayton Services, the company contracted by Denholtz Properties to perform vibration monitoring services. If you did not receive a letter and believe you should have or if you have questions regarding the inspection, please contact Alyssa with Dayton Services at 856-842-1010.
December 19, 2024
  • Storm and sanitary work continue at the north end of the site.
  • Bulkhead installation is in progress.
  • While some vibration may be felt in the surrounding area, there have been no exceedence events reported by Denholtz' vibration monitoring company.
  • Crushing of material from demolition has been completed, but Denholtz may have additional crushing in the future as they accumulate more concrete from excavationalong the old bulkhead.
  • Condo building test pile installation will be completed in a couple of weeks.
  • Dayton Inspection Services will be sending out another round of letters offering internal and/or external structural inspections, as they progress with another phase of bulkheading.
December 6, 2024
  • Denholtz Properties is continuing storm and sanitary sewer work at the north end of the site.
  • Crushing of material from demolition has been completed. There may be some additional crushing in the future as Denholtz Properties accumulates more concrete from excavation along old bulkhead.
  • Bulkhead sheet installation at the south end of the property is progressing smoothly. While some vvibration may be felt in the surrounding area, there have been no exceedence events reported by the vibration monitoring company.
  • Condo building test pile installation will be completed in a couple of weeks.
November 22, 2024
  • Crushing of material from demolition has been completed. There will be additional crushing in the future as Denholtz accumulates more concrete from excavation along old bulkhead.
  • The bulkhead contractor has material deliveries scheduled for Monday 11/25 and Tuesday 11/26.
  • The sitework contractor has begun sanitary sewer work at the north end of the site, along River Street.
  • Bulkhead sheet installation at the south end of the property is progressing amoothly. While some vibration may be felt in the surrounding area, there have been no exceedance events reported by the vibration monitoring company.
  • Condo building test pile installation will be pushed to early December as Denholtz still needs to relocate material from that area.
November 8, 2024
  • Concrete crushing is in progress and is expected to continue for another 2 weeks. In an effort to mitigate the dust created by the crushing and by the machine traffic on site, Denholtz Properties will begin utilizing a water truck starting Friday 11/8/24.
  • Early next week, Denholtz Properties will install stone tracking pads at active construction traffic areas transitioning from exposed soil to paved roadway.
  • Bulkhead sheet installation at the south end of the property is progressing smoothly. While some vibration may be felt in the surrounding area, there have been no exceedance events reported by the vibration monitoring company.
  • Condominium buidling test piles are likely going to be installed the week of 11/25/24.

November 4

  • Concrete crushing is in progress and is anticipated to take several weeks. The contractor is hosing down the material regularly to mitigate the dust created by this process.
  • Bulkhead construction has begun at the south end of the property, with the installation of sheets.
  • Vibration monitoring is being performed with any alerts being sent directly to the bulkhead contractor and developer.
  • Additional inspectionsare being scheduled and completed for neighbors impacted by test piles installed for the future condominium building.
October 25, 2024
  • Denholtz Properties has confirmed that all inspections have been completed for those residents within 200' of the bulkhead installation site, who responded to their letters and permitted access.
  • The turbidity barrier on the waterward side of the bulkhead has been installed to provide additional protection from soil getting into the water, as per the NJDEP.
  • Concrete crushing has begun and will continue for a few more weeks. The Borough has reached out to Denholtz Properties to ensure watering of the concrete is being implemented.
October 17, 2024
  • A letter from Dayton Inspection Services was mailed to all effected property owners on October 2, 2024, offering pre-construction photographic inspections, to establish existing conditions prior to the start of upcoming construction. Please contact Dayton Inspection Services, Inc. at 877-734-7664 to schedule an appointment.
  • Over the next 4-5 days, machinery will be delivered to the site by both the bulkhead contractor and site contractor. Bulkheading will begin, weather permitting, within the next two weeks. Vibration monitors will be installed along the Eastern perimeter of the project site prior to the installation of bulkheading. The bulkhead contractor met with the New Jersey Department of Environmental Protection on-site to review additional preventive measures to ensure compliance.
  • Concrete crushing will begin over the next week.